The following table summarises factors that should typically be considered in an assessment of viability and indicates data sources.
| Upfront costs | Data Source |
|---|---|
| Capital cost of equipment & supporting infrastructure | Quotes from manufacturers and suppliers |
| Design and installation costs | Quotes from consultants, suppliers, contractors or Quantity Surveyor estimate |
| Cost of land take, plant space & ancillary structures, and any other design aspects/changes | Quantity Surveyor estimates and quotes from suppliers/contractors where relevant |
| Financing costs | Developer, ESCO, financing entity |
| Operating costs/charges | Data Source |
|---|---|
| Amount of energy supplied | Energy strategy/feasibility study. Compare with ESCO assumptions where relevant |
| Operating and maintenance costs – systems installed in individual buildings | Information from manufacturers and suppliers. |
| Operating and maintenance costs – shared systems | Prospective ESCO or assumptions in energy strategy/feasibility study |
| Energy prices for heat and electricity (extent of occupier dependence) | Prospective ESCO |
| Standing charges to building owners | Prospective ESCO |
| Upfront income & cost transfer | Data Source |
|---|---|
| Grant funding | Applicant |
| Third party financing & loans | Applicant |
| ESCO financing | Applicant; also see Making Energy Service Companies Work: Guidance and Advice on Setting Up and Delivering an ESCO www.lep.org.uk/files/?ref=FC2M4S3Z-18 |
| Any property sale value uplift realisable | Surveyors or estate agents |
| Ongoing income & charges | Data Source |
|---|---|
| Value of energy exported | Prospective ESCO |
|
Current fiscal incentives, e.g. ROCs Prospective incentives e.g. renewable heat, feed in tariffs, tax breaks |
Prospective ESCO; various Government departments and agencies involve in administering them: www.ofgem.gov.uk, www.hmrc.gov.uk, www.decc.gov.uk, www.berr.gov.uk |
Note: due to commercial sensitivity, it is unlikely that full details of all of the above costs, sources of income or funding arrangements will be provided in the application but you should, through regular communication, try and build a relationship with the developer where they feel comfortable explaining their thinking around these issues.